I-90: Cedars to Dudley

Concrete barrier from mileposts 32-36 will be upgraded or added to the median to prevent crashes from vehicles crossing over.

To add the barrier, the median will be paved, which will also provide a wider shoulder.

Paused for winter
Contact us

Potholes

Severe potholes formed in this area in January 2022, and ITD shut down the lane until emergency repairs could be completed by a contractor.

The department also added money to this project to repave the road section, which will help prevent such severe potholes from forming in the future.

July 2022

Work begins

Construction begins, along with several other projects east of I-90.

Read more

Project
Updates

As of mid October work has paused for the winter. The contractor was only able to complete the eastbound lanes in 2022, so construction will resume next year to resurface the westbound lanes and redo some of the pavement placed on the eastbound lanes that didn’t meet specifications. Barrier will also be installed in 2023 due to a cement shortage.

© Copyright 2023 Idaho Transportation Department Visit ITD Website

I-90 Cedars to Dudley: contact us

Default Project Comment Form
Maximum upload size: 8MB
Maximum upload size: 104.86MB

Signup Form