ID-41: Mullan to Prairie

An expanded highway will help meet the growing traffic demands on this highly-used corridor between Rathdrum and Post Falls.

The highway will be expanded to four lanes divided by a 50-foot median where possible. Depending on the location, intersection improvements will add capacity, provide signalization or limit certain movements to facilitate mobility through the whole corridor. A path will be constructed to the east of the highway.

Comment Form
Corridor construction schedule
2020 - 2022
Traffic impacts
Check 511
I-90 interchange construction starts
2023
Contact us

Intersection changes

Two new signals at 16th and Hope avenues will be installed, with necessary right and left turn lanes added to their current configurations.

Both Poleline and Prairie avenues will feature dual left turn lanes onto the highway. Right turn lanes will be added at Poleline Avenue to head south or north on the highway, and Prairie Avenue will feature a right turn lane for both directions on ID-41. There will also be two dedicated through lanes at the intersection for traffic on Prairie Avenue.

Non-signalized intersections

After construction, movements at non-signalized intersections will be guided by small, curbed medians. Drivers on the highway will be able to turn right or left across traffic, but drivers on the side street will only be able to turn right onto the highway. Drivers on side streets will be able to make U-turns at the nearest signal to change directions or to access businesses on the other side of the highway.

Although drivers will be able to use new left turn lanes on the highway to access 12th Avenue,  a curbed median will only allow right turns onto the highway after construction.

Mullan intersection

Several projects will tie into the Mullan intersection, but major changes aren’t planned for it until the nearby interchange is reconstructed.

Learn about future Mullan intersection

Corridor construction

All work to expand ID-41 is planned for completion in 2022.

The existing highway will essentially become the southbound lanes of the new highway, allowing much of the work to be constructed with minimal impact.

Once work starts, traffic will continue to run on the current lanes while two new lanes and the railroad overpass are built to the east. Once those lanes are finished, traffic will be moved onto that section while the old section is reconstructed.

Download fact sheet

Project
Updates

Work is now underway in the corridor. Read more.

© Copyright 2020 Idaho Transportation Department Visit ITD Website

ID-41: Prairie to Lancaster

Default Project Comment Form
Maximum upload size: 8MB
Maximum upload size: 52.43MB

Sign up

Signup Form