Upgrading the existing pipe at Whiskey Creek with a bottomless arch culvert will allow more fish to swim upstream.

The 1979 pipe at milepost 44 is also nearing the end of its design life, with the replacement funded by the Bonneville Power Administration, the Nez Perce Tribe, U.S. Forest Service and ITD. Construction is scheduled to start late August 2020.

Only one lane open
Starts late August
Complete mid-October