I-90: Osburn to Wallace

Less than three miles will be reconstructed from roughly milepost 58 to milepost 61.

Based on life-cycle cost analysis and current market prices, existing concrete sections will be replaced with asphalt. Guardrail will also be updated.

Read More

Construction

It will take two seasons to resurface this section of I-90, with each season tentatively scheduled for five months.

One lane in each direction will remain open, with all traffic shifted onto one bound at a time to give crews room to work.

Ramps at the Silverton Interchange will be closed each season, depending on which set of lanes are being worked on, with temporary detours to Osburn in place.