Glenns Ferry to Cold Springs Pavement Rehab
This project will restore pavement between Cold Springs and Glenns Ferry
ITD will rehabilitate roughly 7 miles of concrete pavement on I-84 west of Glenns Ferry from mile point 114-121. The work involves placing new concrete and will take place over two construction seasons. During the 2020 season traffic will be shifted to a two-way, two-lane configuration in the eastbound lanes while work is completed on the westbound lanes. During the construction season of 2021, work will be completed on the eastbound lanes while traffic will be diverted to the westbound lanes.