The new interchange design will serve the Fort Hall community and the traveling public for many years.
ITD is working with the Shoshone-Bannock Tribes, the local community and the public to design a new interchange at Exit 80 (Fort Hall) on Interstate 15.
Read MoreExit 80 (the Fort Hall Interchange) is the primary entrance into the Fort Hall community from Interstate 15. The current interchange was constructed in 1958.
The new interchange design will include:
You can now receive project updates directly from ITD via email. Click here to sign up!
December 13, 2022
Construction crews are beginning clearing and grubbing work in the median for the median detour. They are also working on driving piles for temporary shoring at Ross Fork Creek.
Motorists should carefully follow signs and posted speed limits while travelling through the construction area. Motorists should also be aware of trucks entering the highway from the median at lower speeds. Drivers are encouraged to check https://511.idaho.gov or the 511 app to keep track of road conditions and construction.
Open house
ITD will host an open house at the Shoshone-Bannock Casino Hotel on May 15, 2019 to share final design plans for the new interchange. Please drop in anytime between 4 and 6 p.m. to speak with project staff, review plans and give comments.