The new interchange design will serve the Fort Hall community and the traveling public for many years.
ITD is working with the Shoshone-Bannock Tribes, the local community and the public to design a new interchange at Exit 80 (Fort Hall) on Interstate 15.
Read MoreExit 80 (the Fort Hall Interchange) is the primary entrance into the Fort Hall community from Interstate 15. The current interchange was constructed in 1958.
The new interchange design will include:
You can now receive project updates directly from ITD via email. Click here to sign up!
August 14, 2023
Beginning tonight the first girder placement will be done. The next girder placements will be on 8/16, 8/21, and 8/23.
April 7, 2023
Contractor Sundt-Cannon is currently finishing the culverts under the northbound road at Ross Fork Creek and Town Lateral. Once this is complete, they will move the traffic currently on the detour back to the northbound lanes. This is set to occur April 10th at night.
Once the traffic has been moved back to the northbound lanes, Sundt-Cannon will work to complete the tie-ins to the crossover on the southbound side. When completed, the southbound traffic will be moved on to the median detour lanes. This is set to occur April 17th at night.
December 13, 2022
Construction crews are beginning clearing and grubbing work in the median for the median detour. They are also working on driving piles for temporary shoring at Ross Fork Creek.
Motorists should carefully follow signs and posted speed limits while travelling through the construction area. Motorists should also be aware of trucks entering the highway from the median at lower speeds. Drivers are encouraged to check https://511.idaho.gov or the 511 app to keep track of road conditions and construction.