Eagle Rd, Franklin to Leslie Widening Project

This project will add a third southbound lane on SH-55 (Eagle Road) between Franklin Road and E. Leslie Drive.

Work will occur primarily at night (between 10:00 pm and 5:00 am) due to high traffic volumes within the corridor. Nightly work will conclude each day before the morning commute begins.

Project Start
Fall 2021
Project Complete
Spring 2022
Contractor
TBD
Contact us

Project Features

  • Adding 3rd  southbound lane
  • Work to occur primarily at night (10:00 pm to 5:00 am)
September 2011
STAR Agreement signed between the developer, ITD, and ACHD. The agreement included three phases of roadway improvements.
November 2013
Complete Phase 1 Construction (construction of River Valley Street, Records Avenue, Village Drive, and improvements to Eagle Road and Fairview Avenue)
2013
Village at Meridian opened
April 2017
Complete Phase 2 Construction (addition of third northbound lane on Eagle Road)
Summer 2021
Begin Phase 3 Construction