Eagle Rd /ID-44 Intersection Construction Project

New auxiliary lanes and additional left turn lanes will improve safety and mobility at this intersection.

This intersection serves more than 70,000 drivers each day. The new design will increase capacity at the intersection, reducing overall delay and improving safety. Details of the improvements are below.

Project Complete
Fall 2021
Contractor
Knife River
Anticipated Cost
$8.9 million
Contact Us

Conventional Design

Highlights of the new design include:

  • Eliminate free-running rights – safer for pedestrians and cyclists!
  • Add east- and westbound auxiliary lanes for additional through-put.
  • Add second left turn lane on west- and southbound legs.

November 2014
Concept Report and Feasibility Study completed
October 2018
Complete preliminary design
November 2018
Public meeting for comment on preliminary design
2019
Complete final design
February 2021
Begin construction
March 2021
Design altered to conventional signalized intersection
Fall 2021
Construction complete
June 2021

New traffic pattern starts June 3, 2021

Traffic will shift to allow crews to work on corners.

April 2021

Eagle Rd./ID-44 Pop Up meetings

ITD held pop-up meetings to share information about the design

3/23/2021

New information on updated design

Details about project design and features.

3/18/2021

ITD proceeds with new design for improvements

ITD has adjusted the design to be a conventional, signalized intersection with additional capacity.

Project
Updates

Construction is underway.

ITD will send email updates to keep stakeholders informed. Please sign up!