Eagle Rd /ID-44 Intersection Construction Project

A new type of intersection will soon be under construction at Eagle Rd. and ID-44 in Eagle.

The Idaho Transportation Department will begin construction of a continuous flow intersection (CFI) in February 2021. The project will improve the intersection at Eagle Road and ID-44 by reducing congestion at this highly traveled intersection that serves more than 70,000 drivers each day.

How will the CFI work at Eagle Rd. and ID-44?

Watch this video to see how you’ll drive through the CFI. Half CFI video

November 2014
Concept Report and Feasibility Study completed
October 2018
Complete preliminary design
November 2018
Public meeting for comment on preliminary design
2019
Complete final design
February 2021
Begin construction
Summer 2021
Construction complete

Continuous Flow Intersection (CFI)

A CFI allows left-turning traffic and through-traffic to move at the same time in the east and west direction. Vehicles heading north and south on Eagle Road move into dedicated “right turn bypass” lanes to turn more efficiently. The layout eliminates the need for a dedicated left-turn green phase, which improves the capacity of the intersection and reduces delays. The design also includes pedestrian signals and crossings.

February 1, 2021

Eagle Rd. & ID-44 Project Update #1

Email announcing construction is coming in late February.

Eagle Rd./ID-44 Email update #1
February 18, 2021

Eagle Rd. & ID-44 Project Update #1

Email announcing construction begins February 22, 2021

Eagle Rd./ID-44 Email update #2

Project
Updates

Construction is scheduled to begin the week of February 22, 2021.

ITD will send email updates to keep stakeholders informed. Please sign up!