North Idaho Bridges

Four bridges and three culverts will be replaced from 2019 to fall 2020.

Each structure will be under construction for two to three months with one lane of travel open. Flaggers or temporary signals may be on site.

2020 work
to begin early April
2-3 months
Per bridge
Road conditions
Check 511 for traffic updates
Contact us

Schedule

Work is planned to occur at these locations, in relative order, in 2020:

Work at these locations was completed in 2019:

Asset 5
October 2019

Little Hangman Creek complete

The Little Hangman Creek structure is completed, and the bridge at Texas Creek is scheduled to finish later this month. Work paused at Butcher Creek as contractors resolved an issue with the girders but is on track to be completed in mid-November.

Butcher Creek delays
Asset 5
September 2019

Construction at three bridges continues

Work at Little Hangman Creek is expected to be done in mid-September, with work still ongoing at Butcher Creek and Texas Creek.

Asset 5
August 2019

Texas Creek begins

Work continues on Little Hangman Creek and Butcher Creek. Construction is scheduled to begin on August 26 at Texas Creek.

Project
Updates

Kalispell Creek is underway, with work at Santa Creek planned to start early May. Construction this year also includes Round Prairie Creek and Cedar Creek, and all projects will be finished in fall 2020.