North Idaho Bridges

Four bridges and three culverts will be replaced from 2019 to 2021, with the possibility of work over the winter.

Each structure will be under construction for two to three months with one lane of travel open. Flaggers or temporary signals may be on site.

2019 work
to begin late May
2-3 months
Per bridge
Road conditions
Check 511 for traffic updates
Contact us

Schedule

Work is planned to occur at these locations, in relative order, in 2019:

Work is planned to occur at these locations, in relative order, in 2020:

1
Asset 5
August 2019

Texas Creek begins

Work continues on Little Hangman Creek and Butcher Creek. Construction is scheduled to begin on August 26 at Texas Creek.

Project
Updates

Work at Little Hangman Creek is expected to be done in mid-September, with work still ongoing at Butcher Creek and Texas Creek.