I-84 Sealcoat, Broadway to Eisenman

This seal coat will preserve the pavement and create a smooth driving surface.

ITD will sealcoat the travel lanes on I-84 from the Broadway to Eisenman interchanges May 22 - June 28. This project will also cover the ramps at Broadway, Gowen, Eisenman and Blacks Creek Interchanges.

Reduced lanes and detours will be in place for traffic control measures throughout the project. Some delays should be anticipated.

Estimated Budget: $2.2M

Traffic Impacts

Expect delays as I-84 traffic lanes will be reduced in the work zone.
The Eisenman, Gowen, and Broadway Interchanges will be completed on Saturday’s and Sundays only-see the preliminary schedule below. Check 511 for the most up to date information on ramp closures and detours.

Working

Interactive Comment Map

Click on map to place comment.

View Map
May 22 & 23
Project Start @ Eisenman Interchange
May 29 & 30
Detours @ Gowen Interchange
May 31 & June 1
Lane Closures @ Gowen Road
June 2 & 3
Lane Closures @ Blacks Creek Road
June 12 & 13
Detours @ Broadway Interchange
June 20th
Work substantially complete

Project
Updates

Work is anticipated to begin on May 22nd at Eisenman Interchange. Expect preliminary staging and traffic control setup on Friday May 21st. For Eisenman Interchange, add travel time to accommodate for signed detours.

© Copyright 2021 Idaho Transportation Department Visit ITD Website

Contact the Project Team

Default Project Comment Form
Maximum upload size: 8MB
Maximum upload size: 52.43MB

Sign Up for Email Updates

Signup Form