I-84, Sand Hollow Road Bridge Rehabilitation

The road surface on the bridge will be rehabilitated

Work is limited to the Sand Hollow Road bridge spanning I-84. Crews will mill off the top layer of the existing asphalt. Then, using high-powered water pressure, a process called "hydroblasting," the top layer of the bridge deck will be removed. Fresh concrete pavement will be laid down to create a new surface and extend the life of the bridge. New asphalt on the approaches to the bridge will ensure a level transition between the road and bridge. New guardrail on bridge parapets will improve safety.

Comment Form
Traffic Impacts
Click for 511 info
Project End
End of October 2019
Hydroblasting Video
Click Here
Canyon County Bridge Rehabs

Traffic Impacts

Traffic on I-84 will not be impacted with this project.

The bridge over I-84 will be closed from June 3 to mid-July for demolition. Both lanes of Sand Hollow Rd. will open from mid-July through mid-September to accommodate farm equipment during peak harvest season.

The road will be reduced to one lane at the end of Summer until project completion in November. A width restriction will be in effect. Those needing to move wide loads across the bridge can be accommodated by contacting project manager Julie Muth at 208.454.7710