The Idaho Transportation Department paved 13 miles of SH-45, between the SH-78 junction (Walters Ferry) and Deer Flat Road (Nampa).

These improvements will extend the life of the road.

Paving complete!
Thank you for your patience.
Sign up for email updates
Click here
Questions?
Call Kate Wallace (208) 377-9688
Construction update

Improvements to SH-45 included:

  • Resurfacing the bridge deck at Mora Canal
  • Removing the existing pavement and resurfacing the highway between SH-78 junction (Walters Ferry) and Deer Flat Road (Nampa)
  • Widening the turning radius on SH-45 at Missouri Avenue and at Patterson Avenue
  • Paving driveway approaches and shoulder work

This fall, crews will return to the Mora Canal and work underneath the bridge. There will be no impacts to traffic. Thank you for your patience during construction.

Working

Interactive Comment Map

Click on map to place comment.

View Map
Mid-May 2022
Construction begins at Mora Canal bridge
Late June 2022
Road repaving work begins
Early September 2022
Road repaving is completed
November 2022
Final construction activities take place at Mora Canal bridge